Study guide · General Building (B) · Core Trades

Building Envelope: The Rules the Exam Asks For

About 27 minutes · 7 sections

What this guide covers

Core Trades has four smaller slices beyond plumbing, electrical, and HVAC: concrete, earthwork and surveying, insulation and energy, and roofing. Together they are 38 rules. Half are arithmetic: yards of concrete, a stake elevation, a roof in squares. The rest are numbers and sequences from four codes. Six inches of fall in ten feet. One square foot of vent per 150. Drip edge under at the rake, over at the eave. This Brief carries them at the grain the exam tests them.

Key terms

Class I vapor retarder
A ground cover that limits water vapor from the soil; the code names it for crawl-space floors.
U-factor
Heat flow through a whole assembly, air films included; lower is better.
R-value
A layer's resistance to heat flow; higher is better. Layers add in series.

The rules the exam tests

5 rules · 2 min

Concrete

  1. When you anchor into concrete, follow ACI 318 plus Section 1905 of the Building Code.

    ACI 318 covers cast-in headed bolts, headed studs, and hooked J- or L-bolts, plus post-installed expansion, undercut, screw, and adhesive anchors. Section 1905 of the Building Code supplements that standard, so both apply to the anchor design together.

    On the job

    The Building Code hands anchoring in concrete to ACI 318 and names the anchor types the rule reaches. Holding reinforcing bars in position is ACI practice, and chairs are one common way to do it.

    Exact wording

    Anchoring to concrete follows ACI 318 as supplemented by Section 1905 of the Building Code. The rule covers cast-in headed bolts, headed studs, and hooked J- or L-bolts, and post-installed expansion, undercut, screw, and adhesive anchors.

    Building Code § 1901.3

  2. An isolation joint separates the slab from columns, walls, and footings.

    An isolation joint runs full depth through the slab on grade, with a compressible filler strip in the gap against the column, wall, or footing, so the slab can shrink, curl, and move without binding on the fixed element and cracking.

    On the job

    Full depth at a fixed element is what distinguishes it from a control joint, which is partial depth in the open field of the slab.

    Exact wording

    An isolation joint is a full-depth separation, with a compressible filler strip, between a slab on grade and fixed parts of the building such as columns, walls, and footings; it lets the slab shrink, curl, and move without binding on the fixed element and cracking.

    Standard trade practice

  3. The slab will crack as it shrinks. A control joint decides where the crack goes.

    A control joint, also called a contraction joint, is a weakened plane tooled or saw-cut partway into a slab at regular spacing. Shrinkage cracking then opens along that straight line instead of at random.

    On the job

    The slab will crack as it shrinks; the control joint decides where.

    Exact wording

    A control joint, also called a contraction joint, is a weakened plane tooled or saw-cut partway into a slab at regular spacing so that shrinkage cracking opens along that straight line instead of at random.

    Standard trade practice

  4. You weaken the concrete when you add water at the truck beyond the mix design.

    Water added past the mix design raises the water-cement ratio with no cement added. The concrete cures lower in compressive strength and more porous than the mix design called for. Workability bought at the truck is paid for in strength.

    On the job

    Workability bought with water at the truck is paid for in strength.

    Exact wording

    Adding water to a ready-mix load beyond the amount in the mix design raises the water-cement ratio without adding cement, so the cured concrete has lower compressive strength and is more porous than the mix was designed to be.

    Standard trade practice

  5. Wet a dry, absorbent base ahead of the truck on a hot, dry day.

    A dry base pulls mix water out of the bottom of fresh concrete, so that surface ends up weak and cracks early. Leave the base damp right through — moist, with no standing water anywhere on it when the concrete arrives.

    On the job

    Damp, not puddled: standing water raises the water-cement ratio at the bottom instead.

    Exact wording

    On a hot, dry day a dry, absorbent base is wetted ahead of the truck so it is moist but has no standing water, because a dry base pulls mix water out of the bottom of fresh concrete, weakening that surface and inviting early cracking.

    Standard trade practice

Next chapter: Earthwork and surveying · about 2 minBack to contents
4 rules · 2 min

Earthwork and surveying

  1. You need a geotechnical investigation where shallow footings bear on compacted fill over 12 inches deep.

    A geotechnical investigation is a report on the soil conditions at the site. Where the compacted fill under a shallow footing is more than 12 inches deep, that report must specify site preparation, the fill material, the test methods for maximum dry density and optimum moisture, the maximum thickness, the field test for in-place dry density, the minimum acceptable in-place dry density as a percent of that maximum, and the number and frequency of field tests.

    On the job

    is the tested idea: the in-place dry density expressed as a percent of the laboratory maximum dry density. The 12-inch fill depth is the trigger for the whole investigation.

    Exact wording

    Where shallow foundations bear on compacted fill more than 12 inches deep, a geotechnical investigation is required. It must specify site preparation, the fill material, the test methods for maximum dry density and optimum moisture, the maximum lift thickness, the field test for in-place dry density, the minimum acceptable in-place dry density as a percentage of that maximum, and the number and frequency of field tests.

    Building Code § 1803.5.8

  2. Grade every lot so surface water runs away from the foundation walls.

    The grade must drop at least 6 inches away from the foundation within the first 10 feet. Where lot lines, walls, slopes, or other barriers prevent that fall, drains or swales must carry water away from the structure. Impervious surfaces within 10 feet of the foundation slope at least 2 percent away from the building.

    On the job

    6 inches in 10 feet is the tested number; 2 percent on paving is its neighbor. The exception is the qualifier: a swale substitutes where the fall cannot be built.

    Exact wording

    Lots are graded to drain surface water away from foundation walls. The grade must fall at least 6 inches within the first 10 feet. Where lot lines, walls, slopes, or other barriers prevent that, drains or swales must carry water away from the structure. Impervious surfaces within 10 feet of the foundation slope at least 2 percent away from the building.

    Residential Code § r401.3

  3. Your two working day notice is not permission to dig. Wait for every positive response.

    Before opening an excavation, find the approximate location of subsurface installations such as sewer, telephone, fuel, electric, and water lines. Notify the regional notification centers for the area and any known owners not in a center at least two working days before digging; emergency repair work is exempt. As the excavator, don't start until you've marked the area as Government Code 4216.2 requires and every known owner or operator of lines in the project responds that its lines are located or it has none in the way.

    On the job

    Two working days is a notice lead time, not a permission clock. Digging waits for the marking and the positive responses; the safety Brief carries the rest of the excavation article.

    Exact wording

    Before opening an excavation, the excavator determines the approximate location of subsurface installations such as sewer, telephone, fuel, electric, and water lines. Excavation may not begin until the excavator has marked the excavation area as Government Code 4216.2 requires and has received a positive response from every known owner or operator of subsurface installations within the project, confirming their lines are located or that they have none in the way. The regional notification centers for the area, and any known owners of subsurface facilities that are not members of a center, are advised at least two working days before digging starts, except for emergency repair work.

    Code of Regulations, Title 8 (Construction Safety Orders) § 1541 ↗

  4. Close every level run back on the it started from.

    A run may cross several instrument setups. Compare the closing elevation with the benchmark's known value: that difference is the error in the run. If the run doesn't close within tolerance, rerun it before anyone builds to those stakes.

    On the job

    An elevation carried four setups away has no check on it until the loop closes.

    Exact wording

    A line of levels run through several instrument setups is continued back to the starting benchmark and the closing elevation is compared with the benchmark's known value; the difference is the error in the run, and a run that does not close within tolerance is rerun before anything is built to its stakes.

    Standard trade practice

Next chapter: Insulation and energy · about 8 minBack to contents
17 rules · 8 min

Insulation and energy

  1. Give a ventilated crawl space at least 1 square foot of vent per 150 square feet.

    Net area is the free opening through the covering: at least 1 square foot per 150 square feet of under-floor area. One opening goes within 3 feet of each outside corner. The cover's holes are no larger than 1/4 inch.

    On the job

    1 in 150 is the tested ratio, with an opening near each corner. A ground vapor retarder is the one thing that reduces it.

    Exact wording

    A ventilated crawl space needs ventilation openings with a net area of at least 1 square foot for each 150 square feet of under-floor area, with one opening within 3 feet of each outside corner, covered by material with openings no larger than 1/4 inch.

    Residential Code § r408

  2. If you cover the ground with an approved Class I vapor retarder, vent at 1/1,500.

    The opening within 3 feet of each outside corner is no longer required, provided you place the openings so air crosses the space from side to side. Measure the 1/1,500 against the under-floor area.

    On the job

    The ground cover earns the reduction: 1 in 1,500 instead of 1 in 150, and the corner rule relaxes only if the openings still cross-ventilate.

    Exact wording

    Where the ground is covered with an approved Class I vapor retarder, the opening area may drop to 1/1,500 of the under-floor area, and the corner-opening rule no longer applies provided the openings are placed to give cross ventilation of the space.

    Residential Code § r408

  3. Cover the exposed earth of an unvented crawl space with a continuous Class I vapor retarder.

    Lap the retarder's joints 6 inches and seal or tape them. Run the edges at least 6 inches up the stem wall, attached and sealed to the stem wall or to the insulation. Then either run continuous mechanical exhaust at 1 cfm per 50 square feet of crawl-space floor, with a duct or transfer grille as the air pathway to the common area, or use one of the other listed conditioning options.

    On the job

    The unvented option trades vents for a sealed ground cover plus conditioning. The 6-inch lap and 6-inch stem-wall run are the neighbors to the vapor-retarder definition.

    Exact wording

    An unvented crawl space covers the exposed earth with a continuous Class I vapor retarder, joints lapped 6 inches and sealed or taped, edges run at least 6 inches up the stem wall and attached and sealed to the stem wall or to the insulation. It then needs either continuous mechanical exhaust at 1 cubic foot per minute per 50 square feet of crawl-space floor with an air pathway to the common area (a duct or transfer grille), or one of the other listed conditioning options.

    Residential Code § r408

  4. Keep at least 1 inch of air above the insulation at the eave vent.

    Where you install eave or cornice vents, keep blocking, bridging, and insulation from blocking free air flow. Leave at least 1 inch of space between the insulation and the roof sheathing, and at the vent.

    On the job

    The rule is the air path: 1 inch between insulation and sheathing, and at the vent. Baffles are the usual way to keep that space open when insulation is blown in; the code names the result, not the device.

    Exact wording

    Where eave or cornice vents are installed, blocking, bridging, and insulation may not block the free flow of air. At least a 1-inch space is provided between the insulation and the roof sheathing, and at the location of the vent.

    Residential Code § r806.3

  5. U-factor rates heat flow through the whole assembly. R-value rates one layer.

    The assembly is the complete component—fenestration, wall, floor, roof, or ceiling—and the U-factor is its overall coefficient of thermal transmittance, including the air-film resistance at both surfaces. Units: Btu per hour per square foot per degree Fahrenheit.

    On the job

    U-factor rates heat flow through the whole assembly, air films included; lower is better. R-value rates one layer's resistance. The exam tests which is which.

    Exact wording

    A U-factor is the overall coefficient of thermal transmittance of a fenestration, wall, floor, roof, or ceiling component, in Btu per hour per square foot per degree Fahrenheit, including the air-film resistance at both surfaces.

    Energy Code § 100.1

  6. When you calculate prescriptive compliance by hand, use the values printed in JA4.

    JA4 carries the U-factor, C-factor, and thermal-mass data that all residential and nonresidential prescriptive compliance calculations must use. Only Energy Commission-approved compliance software may adjust those printed values, only by the appendix's procedures and within its limits — never by hand.

    On the job

    Prescriptive compliance reads assembly values from JA4, and the only thing allowed to move them is approved software following the appendix's own procedures — a hand reader takes the printed number.

    Exact wording

    The Energy Code's Joint Appendix JA4 carries the U-factor, C-factor, and thermal-mass data that must be used for all residential and nonresidential prescriptive compliance calculations. Energy Commission-approved compliance software may adjust the printed values, only by the appendix's own procedures and within its limits, and never when the tables are used manually.

    Energy Code § ja4

  7. You may ask the Energy Commission to approve an alternative U-factor for an assembly JA4 omits.

    The route opens where the JA4 tables do not adequately represent the assembly. The permit applicant or the product's manufacturer makes the request, and the Executive Director grants approval after reviewing the submittal and supporting information on their merits. Acceptable calculation methods are ASHRAE-based: hot-box, hot-plate, or heat-flow-meter testing, series/parallel-path calculation for wood framing, and the modified zone method for metal framing. An approved component is published as an addendum to the appendix.

    On the job

    An assembly type the tables do not adequately represent goes to the Executive Director on an ASHRAE-method submittal — a different route from substituting one component inside a wood-framed type the tables already list.

    Exact wording

    Where an assembly is not adequately represented in the JA4 tables, the permit applicant or the product's manufacturer may ask the Energy Commission to approve an alternative U-factor for it. The Executive Director grants that approval after reviewing the submittal and supporting information on their merits; acceptable calculation methods are ASHRAE-based, such as hot-box, hot-plate, or heat-flow-meter testing, series/parallel-path calculation for wood framing, and the modified zone method for metal framing. An approved component is published as an addendum to the appendix.

    Energy Code § ja4

  8. JA4 sorts its tables by roofs, walls, and floors, then by construction type.

    Inside those groups, every printed value carries its own letter-and-number coordinate. The coordinate is that value's name, so an assembly in JA4 is called out by its coordinate.

    On the job

    The coordinate (4.3.1-H3) is how an assembly is named on compliance documents — the plan checker reads the coordinate, not a description.

    Exact wording

    The JA4 tables are organized by roofs, walls, and floors, then by construction type, with a letter-and-number coordinate naming each value.

    Energy Code § ja4

  9. R-value rates one layer of insulation. U-factor rates the whole assembly together.

    A complete assembly usually has several layers, and each layer carries its own conductance. U-factor describes the conductance of every component together, so an insulation R-value alone does not describe the overall performance of the assembly.

    On the job

    The exam asks which number describes what: R-value is one layer's resistance, U-factor is the whole assembly's conductance.

    Exact wording

    R-value describes insulation effectiveness, but it does not describe the overall performance of a complete assembly; an assembly usually has several layers, each with its own conductance, and the U-factor describes the conductance of every component together.

    Energy Code § ja4

  10. Prescriptive compliance has two tests. Passing either the R-value or the U-factor is enough.

    You comply prescriptively either way: the insulation's R-value equals or exceeds the R-value required for that envelope feature in your climate zone, or the assembly's overall U-factor is equal to or less than the U-factor required for it.

    On the job

    Two different tests, and passing either one is compliance: the layer's R-value against the table's R-value, or the assembly's U-factor against the table's U-factor.

    Exact wording

    Prescriptive compliance is shown either when the insulation's R-value equals or exceeds the R-value required for that envelope feature in the building's climate zone, or when the assembly's overall U-factor is equal to or less than the U-factor required for it.

    Energy Code § ja4

  11. You run the appendix's worked example when the tables don't cover a wood-framed component.

    Substitute the different component, such as another insulation R-value, into that example: a 2x4 wall framed 16 inches on center. Sum the R-values layer by layer through the cavity path (Rc) and the frame path (Rf), then combine them as [1/Rc × (1 − frame%/100)] + [1/Rf × (frame%/100)]. The framing percent is a lookup in Table 4.1.6, not a guess: conventionally framed walls 25 percent at 16 inches on center and 22 percent at 24 inches; advanced wall systems 17 percent at 24 inches and 4 percent at 48 inches; floors and roofs 10 percent at 16 inches and 7 percent at 24 inches.

    On the job

    Substituting one component inside a wood-framed type the tables already list is a worked-example calculation, not an approval — and the framing percentage is a table lookup, not a guess.

    Exact wording

    For components within wood-framed assemblies that are not represented in the tables, the appendix's example procedure substitutes the different component, such as another insulation R-value, into its worked calculation (a 2x4 wall framed 16 inches on center), which sums the R-values layer by layer through the cavity path (Rc) and the frame path (Rf) and combines them as [1/Rc × (1 − frame%/100)] + [1/Rf × (frame%/100)], with the framing percentage from Table 4.1.6: for conventionally framed walls, 25 percent at 16 inches on center and 22 percent at 24 inches (advanced wall systems 17 percent at 24 inches and 4 percent at 48); floors and roofs 10 percent at 16 inches and 7 percent at 24.

    Energy Code § ja4

  12. The Commission's assembly calculator handles wood, metal, and more advanced assemblies.

    The calculator is part of the Commission's compliance software, and you may use its output in a permit submittal. Mass-type construction is the exception: that work must use approved software.

    On the job

    The calculator is the route for assemblies the hand method does not fit, and for mass construction it is the only route.

    Exact wording

    The Commission's assembly calculator in the compliance software is available for wood, metal, and more advanced assemblies, and its output is usable in a permit submittal; mass-type construction must use approved software.

    Energy Code § ja4

  13. Average the U-factors at the thinnest and thickest tapered insulation. Never average the R-values.

    The prescriptive R-value approach applies to continuous roof insulation tapered for drainage: find the U-factor at the minimum thickness and at the maximum thickness, average those two, and the R-value is the inverse of that average. Dividing the roof into sub-areas by insulation thickness is allowed only under the performance method. Adjusting the appendix's published data is a software matter, not something done when the tables are used manually. An assembly type the tables do not adequately represent takes the approval route instead.

    On the job

    The only inverse in the appendix is the tapered-roof rule, and it averages U-factors, never R-values — the exam's trap is averaging the wrong number.

    Exact wording

    For continuous roof insulation tapered for drainage, the prescriptive R-value approach finds the U-factor at the minimum and maximum insulation thickness, averages those two U-factors, and takes the R-value as the inverse of that average. R-values themselves may not be averaged, and the alternative of dividing the roof into sub-areas by insulation thickness is allowed only under the performance method. Adjustments to the appendix's published data are a software matter and are not made when the tables are used manually; an assembly type the tables do not adequately represent takes the approval route.

    Energy Code § ja4

  14. You may not interpolate between continuous insulation columns when reading Joint Appendix 4 by hand.

    Continuous insulation is insulation uninterrupted by framing that forms a continuous insulating layer, and many JA4 tables carry columns for it. Reading such a table by hand, your proposed continuous insulation's rated R-value must equal or exceed the R-value in the column heading. Only Energy Commission-approved compliance software may credit an in-between amount, using the appendix's Equation 4-1, and never for continuous insulation below R-2.

    On the job

    Reading the table by hand means rounding DOWN to the column you meet, never between columns; interpolation is a software-only move, and only at R-2 or greater.

    Exact wording

    Many JA4 tables carry columns for levels of continuous insulation, which is insulation uninterrupted by framing that forms a continuous insulating layer. When a table is used manually, the proposed continuous insulation's rated R-value must be equal to or greater than the R-value shown in the column heading, and no interpolation between columns is permitted. Only Energy Commission-approved compliance software may account for an in-between amount of continuous insulation, using the appendix's Equation 4-1, and that adjustment may not be used for continuous insulation of less than R-2.

    Energy Code § ja4

  15. You meet the mandatory sections on a new home and pick one of the two standards.

    The mandatory sections are 110.0 through 110.10 plus the mandatory features of Section 150.0. The choice is either the performance standards or the prescriptive standards for the building's climate zone. Additions and alterations follow the modified rules in Section 150.2.

    On the job

    Three layers: the general mandatory sections, the residential mandatory features, and one of two compliance paths. New construction follows 150.1 in full; for additions and alterations, 150.2(a) and (b) modify the 150.1(a) through (c) requirements.

    Exact wording

    A newly constructed single-family residential building meets the Energy Code by satisfying Sections 110.0 through 110.10, the mandatory features of Section 150.0, and either the performance standards or the prescriptive standards for its climate zone. Additions and alterations use the modified rules in Section 150.2.

    Energy Code § 150.1

  16. On the performance path you trade one measure against another. You never trade mandatory features.

    On the performance path, your building complies when its calculated energy use is no greater than the standard design's energy budget, computed with Commission-certified compliance software. Efficiency measures can trade against each other inside that budget. Mandatory features still apply.

    On the job

    Prescriptive means every component meets its table value; performance means the whole building beats a budget, which is how less insulation in one place can be traded for more elsewhere. Mandatory features are not part of the trade.

    Exact wording

    Under the performance approach the building complies if its calculated energy consumption is no greater than the energy budget of the standard design, computed with Commission-certified compliance software. Efficiency measures may trade against one another inside that budget; the mandatory features still apply.

    Energy Code § 150.1

  17. Give the wall between units 50. The entrance door only has to fit tight.

    Walls, partitions, and floor-ceiling assemblies separating dwelling or sleeping units from each other, or from public or service areas, need at least STC 50 tested per ASTM E90, or at least NNIC 45 if field tested per ASTM E336. Alternatively, a registered design professional may establish the STC by engineering analysis, comparing against assemblies rated by ASTM E90 testing. Seal, line, insulate, or otherwise treat penetrations and openings for piping, electrical devices, recessed cabinets, bathtubs, soffits, or heating, ventilating, or exhaust ducts so the rating holds. That requirement does not apply to entrance doors; they need only fit tight to the frame and sill.

    On the job

    STC 50 is the tested number for the wall between units; NNIC 45 is its field-test twin. The entrance door is the qualifier: it is exempt from the rating, but must fit tight.

    Exact wording

    Walls, partitions, and floor-ceiling assemblies separating dwelling units or sleeping units from each other, or from public or service areas, need a sound transmission class of at least 50 when tested per ASTM E90, or a normalized noise isolation class of at least 45 if field tested per ASTM E336. Alternatively, the sound transmission class may be established by engineering analysis, based on a comparison with assemblies whose ratings were determined by ASTM E90 testing, performed by a registered design professional. Penetrations and openings in those assemblies for piping, electrical devices, recessed cabinets, bathtubs, soffits, or heating, ventilating, or exhaust ducts are sealed, lined, insulated, or otherwise treated to keep the rating. That requirement does not apply to entrance doors, which need only fit tight to the frame and sill.

    Building Code § 1206.2

Crawl-space ventilation under R408: vented, vented with ground cover, unvented

  • VentedVent opening area
  • Vented with a Class I vapor retarder on the groundVent opening area
  • UnventedVent opening areaNo such rule in this standard
Next chapter: Roofing · about 5 minBack to contents
10 rules · 5 min

Roofing

  1. Lay asphalt shingles only on a roof slope of 2 in 12 or steeper.

    Section R905.1.1 fixes the underlayment count. Underlayment is the felt or membrane under the shingles. From 2 in 12 (17 percent) up to 4 in 12 (33 percent), install two layers; at 4 in 12 or steeper, one layer.

    On the job

    Two numbers: 2 in 12 is the floor, and the underlayment doubles on slopes below 4 in 12. Exactly 4 in 12 is a one-layer roof. The exam tests both.

    Exact wording

    Asphalt shingles may be used only on roof slopes of 2 in 12 (17-percent slope) or greater. From 2 in 12 up to 4 in 12 (33-percent slope), double underlayment is required in accordance with Section R905.1.1, whose table draws the line: two layers up to 4 in 12, one layer at 4 in 12 or steeper.

    Residential Code § r905.2.2

  2. Use one layer of underlayment under asphalt shingles at 4 in 12 and steeper.

    This is the table for roof areas where Figure R301.2.1.1 does not require wind design, and it offers three options. At 4 in 12 and greater: one layer, applied shingle fashion, lapped 2 inches. From 2 in 12 up to 4 in 12: two layers — a half-width starter strip at the eave, fastened enough to hold it in place, then full sheets lapped half a sheet plus 2 inches. For both, end laps are 4 inches, offset 6 feet, and distortions in the underlayment must not keep the shingles from sealing. Or use a single layer of self-adhering polymer-modified bitumen underlayment complying with ASTM D1970, installed per the underlayment and shingle manufacturers' instructions.

    On the job

    The boundary is the exam's favorite: the table's one-layer item governs at 4 in 12 and above, so 4 in 12 itself is one layer. The laps are the neighbors. This is the no-wind-design table; roofs in areas where Figure R301.2.1.1 requires wind design use the companion table, Table R905.1.1(1), which this guide does not cover.

    Exact wording

    Under the underlayment table for roof areas where wind design is not required per Figure R301.2.1.1, asphalt-shingle underlayment is one of three options. The first, for slopes from 2 in 12 up to 4 in 12, is two layers: a half-width starter strip at the eave fastened sufficiently to hold in place, then full sheets lapped half a sheet plus 2 inches, end laps 4 inches offset 6 feet. The second, for slopes of 4 in 12 and greater, is one layer applied shingle fashion, lapped 2 inches, with the same 4-inch end laps offset 6 feet; for both, distortions in the underlayment may not interfere with the shingles' ability to seal. The third is a single layer of self-adhering polymer-modified bitumen underlayment complying with ASTM D1970, installed per the underlayment and shingle manufacturers' instructions.

    Residential Code § table-r905.1.1-2

  3. Base flashing can be metal or roll roofing. Cap flashing has to be metal.

    Follow the manufacturer's instructions for . Base flashing is corrosion-resistant metal at least 0.019 inch thick, or mineral-surfaced roll roofing weighing at least 77 pounds per 100 square feet. Cap flashing must be corrosion-resistant metal at least 0.019 inch thick.

    On the job

    Base flashing is the lower layer; cap (counter) flashing laps over it. Installation follows the manufacturer's instructions, and 0.019 inch is the tested gauge for either metal layer.

    Exact wording

    Base and cap flashing follow the manufacturer's instructions. Base flashing is corrosion-resistant metal at least 0.019 inch thick or mineral-surfaced roll roofing weighing at least 77 pounds per 100 square feet; cap flashing is corrosion-resistant metal at least 0.019 inch thick.

    Residential Code § r905.2.8.1

  4. Line the valley before the shingles go on.

    The manufacturer's instructions govern the lining, and it goes in before the shingles. An open metal valley needs corrosion-resistant metal from the code's table, at least 24 inches wide. Or use two plies of mineral-surfaced roll roofing: an 18-inch bottom layer and a top layer at least 36 inches wide.

    On the job

    Line the valley before shingling. An open valley gets either 24-inch metal from the code's table or two plies of mineral-surfaced roll roofing, 18 inches on the bottom and at least 36 inches on top; both are tested.

    Exact wording

    Valley linings are installed per the manufacturer's instructions before the shingles. An open metal valley needs lining at least 24 inches wide of a corrosion-resistant metal in the code's table. An open valley may instead use two plies of mineral-surfaced roll roofing, an 18-inch bottom layer and a top layer at least 36 inches wide.

    Residential Code § r905.2.8.2

  5. Line a closed valley with 36-inch smooth roll roofing, self-adhering bitumen underlayment, or an open-valley lining.

    A closed valley is the kind the shingles cover. Use one ply of smooth roll roofing meeting ASTM D6380, at least 36 inches wide; or self-adhering polymer-modified bitumen underlayment meeting ASTM D1970, at least 36 inches wide; or any lining permitted for an open valley. Install the lining per the manufacturer's instructions before the shingles.

    On the job

    A closed valley is covered by shingles, so its lining may be lighter: 36 inches of smooth roll roofing or self-adhering underlayment, or anything an open valley may use.

    Exact wording

    A closed valley, covered with shingles, may be lined with one ply of smooth roll roofing complying with ASTM D6380 and at least 36 inches wide, with self-adhering polymer-modified bitumen underlayment complying with ASTM D1970 and at least 36 inches wide, or with any lining permitted for an open valley; valley linings are installed per the manufacturer's instructions before the shingles.

    Residential Code § r905.2.8.2

  6. Run the underlayment over the drip edge at the eaves. Run it under at the rakes.

    Put a drip edge at the eaves and rake edges of shingle roofs. Lap adjacent pieces at least 2 inches. It must reach at least 1/4 inch below the sheathing and at least 2 inches back onto the deck. Fasten no more than 12 inches on center. Underlayment goes over it at the eaves and under it at the rakes.

    On the job

    Over at the eaves, under at the rakes: the tested sequence. The 2-inch laps, 1/4-inch drop, and 12-inch fastening are the neighbors.

    Exact wording

    A drip edge goes at the eaves and rake edges of shingle roofs. Adjacent pieces overlap at least 2 inches. The drip edge extends at least 1/4 inch below the sheathing and at least 2 inches back onto the deck, fastened at no more than 12 inches on center. Underlayment goes over the drip edge along the eaves and under it along the rakes.

    Residential Code § r905.2.8.5

  7. Slope built-up roofs at least 1/4 in 12. Coal tar may drop to 1/8.

    That slope is a design slope, set for drainage: at least 1/4 in 12, which is 2 percent. Coal-tar built-up roofs are the one carve-out, and their design slope may be as low as 1/8 in 12 (1 percent).

    On the job

    1/4 in 12 is the tested minimum for a built-up roof; the coal-tar exception at 1/8 in 12 is the qualifier the exam likes.

    Exact wording

    Built-up roofs have a design slope of at least 1/4 in 12 (2 percent) for drainage, except coal-tar built-up roofs, which may be as low as 1/8 in 12 (1 percent).

    Residential Code § r905.9.1

  8. Install secondary overflow drains or where perimeter construction would trap backed-up water.

    Perimeter construction is roof edge, such as a parapet, that rises above the roof and would trap water if the primary drains back up. Where roof drains are required, a secondary drain or scupper is required wherever that trapping would occur. Sizing and installation follow Section 1611 and Plumbing Code Chapter 11.

    On the job

    A parapet turns a clogged drain into a pond. The exam tests that the trap condition, not the roof size, triggers the secondary drain.

    Exact wording

    Where roof drains are required, secondary emergency-overflow drains or scuppers are required wherever the roof's perimeter construction extends above the roof so that water would be trapped if the primary drains back up. Their installation and sizing follow Section 1611 and Chapter 11 of the Plumbing Code.

    Building Code § 1502.2

  9. Set your secondary roof drain inlets at least 2 inches above the roof surface.

    A secondary roof drain is the emergency overflow inlet that carries water when the primary drains back up. Its inlet sits at least 2 inches up and no higher than the ponding depth the roof was designed for. Each secondary drain connects one of two ways. Either run separate piping, independent of the primary drains, discharging above grade where occupants or maintenance staff can observe it. Or, where the primary storm drainage system connects to building storm water that connects to an underground public storm sewer, connect the secondary drains to the primary conductor's vertical piping downstream of the last horizontal offset below the roof, and size the combined system for double the local rainfall rate.

    On the job

    Two inches above the roof is the tested figure. The separate system must discharge where someone will notice; the combined route is allowed only where the primary system reaches a public storm sewer, and it is sized for twice the rainfall.

    Exact wording

    Secondary roof drains sit at least 2 inches above the roof surface and no higher than the ponding depth the roof was designed for. They connect one of two ways. A separate piping system, independent of the primary drains, discharges above grade where occupants or maintenance staff can observe it. Or, where the primary storm drainage system connects to building storm water that connects to an underground public storm sewer, the secondary drains may tie into the primary conductor's vertical piping downstream of the last horizontal offset below the roof, with the combined system sized for double the local rainfall rate.

    Plumbing Code § 1101.12.2.2

  10. The counterflashing laps down over the base flashing's upturned edge.

    Counterflashing is separate formed metal let into the chimney's mortar joints above the base flashing. The base flashing turns up against the chimney and the counterflashing covers that upturned edge, so water running down the masonry sheds onto the roof instead of behind the flashing.

    On the job

    Two pieces let the roof and the chimney move independently; the exam asks which piece is which.

    Exact wording

    Counterflashing is the separate formed metal let into a chimney's mortar joints above the base flashing and lapped down over the base flashing's upturned edge, so water running down the masonry is shed onto the roof instead of behind the flashing; base flashing turns up against the chimney, counterflashing covers it.

    Standard trade practice

Next chapter: Envelope arithmetic · about 4 minBack to contents
8 rules · 4 min

Envelope arithmetic

  1. Change the slab or footing thickness from inches to feet before you calculate cubic yards.

    Concrete is ordered by the cubic yard: 27 cubic feet. For a slab or continuous footing, multiply length × width × thickness, then divide by 27. A 2-foot-wide, 1-foot-deep footing 120 feet long is 240 cubic feet, 8.9 cubic yards before waste.

    On the job

    The exam gives footing dimensions and asks for yards. Inches become feet before multiplying, and 27 is the divisor; any waste allowance is a separate estimating judgment, not part of the theoretical volume.

    Exact wording

    Concrete is ordered by the cubic yard, and a cubic yard is 27 cubic feet. For a slab or continuous footing, convert the thickness to feet, multiply length × width × thickness for cubic feet, and divide by 27. Example: a 2-foot-wide, 1-foot-deep footing 120 feet long is 2 × 1 × 120 = 240 cubic feet, or 8.9 cubic yards before waste.

    Standard trade practice

  2. You calculate a round pier footing as a cylinder. The diameter is not the radius.

    Volume is π × radius² × depth in feet, so that product is the cubic feet in one pier. Divide by 27 for cubic yards, then multiply by the number of piers. Twelve 18-inch piers 3 feet deep: radius 0.75 foot, π × 0.75² × 3 = 5.3 cubic feet each, 63.6 total, 2.36 cubic yards.

    On the job

    The trap is the diameter: halve it before squaring. The stem must give diameter, depth, and count.

    Exact wording

    A round pier footing is a cylinder: π × radius² × depth in feet gives cubic feet; divide by 27 and multiply by the number of piers. Example: twelve 18-inch piers 3 feet deep have a radius of 0.75 foot; π × 0.75² × 3 = 5.3 cubic feet each, 63.6 total, 2.36 cubic yards.

    Standard trade practice

  3. Add the backsight to the and subtract the foresight to find the elevation.

    With a builder's level, the backsight is the rod reading on the benchmark and the foresight is the reading on the new point. Benchmark plus backsight is the ; that height minus the foresight is the point's elevation. Benchmark 100.00 plus backsight 4.25 puts the instrument at 104.25, and a foresight of 6.10 leaves the stake at 98.15.

    On the job

    The exam gives a benchmark and two rod readings and asks for a stake elevation. Add the backsight, subtract the foresight. A second setup repeats the pair from a turning point.

    Exact wording

    With a builder's level, the height of instrument equals the benchmark elevation plus the backsight reading. The elevation of a point equals the height of instrument minus the foresight reading on it. Backsights are added; foresights are subtracted. Example: benchmark 100.00, backsight 4.25, so the instrument is at 104.25; a foresight of 6.10 puts the stake at 98.15.

    Standard trade practice

  4. Divide the rise by the run and multiply by 100 to get slope in percent.

    Elevations of 102.50 and 100.00 over 125 feet of run give 2.50 ÷ 125 × 100 = 2 percent. The rise is the difference between the two elevations; the run is the horizontal distance between them.

    On the job

    Rise over run times 100. The exam gives two elevations and a distance and asks for the percent, or gives a percent and a distance and asks for the fall.

    Exact wording

    Slope in percent is the elevation difference divided by the horizontal distance, times 100. Example: elevations 102.50 and 100.00 over 125 feet of run give 2.50 ÷ 125 × 100 = 2 percent.

    Standard trade practice

  5. Count the inside and outside air films as layers when you total R for U-factor.

    U-factor is one divided by the assembly's total R-value. Add every layer's R-value in series, including the inside and outside air films, to get R-total. Layers totaling R-20 give U = 1 ÷ 20 = 0.050.

    On the job

    The exam gives layer R-values and asks for U. Add the layers, then take one over the total. Compliance values come from JA4's tables; the relation is the same.

    Exact wording

    A U-factor is the reciprocal of the assembly's total R-value: U = 1 ÷ R-total, where R-total sums the layer R-values in series, including the inside and outside air films. Example: layers totaling R-20 give U = 0.050.

    Standard trade practice

  6. Multiply the plan area by the on every sloped roof.

    Plan area is the flat footprint shown on the plan, not the sloped surface. One covers 100 square feet of roof surface. The slope factor is √(rise² + 144) ÷ 12 for a rise-in-12 pitch. Divide the roof surface area by 100 for squares, and add waste last. Example: 2,400 square feet of plan area at 6 in 12 has a slope factor of 1.118, so 2,683 square feet, 26.8 squares, 29.5 squares with 10 percent waste, ordered as 30.

    On the job

    Plan area, slope factor, waste, in that order. The exam supplies the pitch or the factor and the waste percent; forgetting the slope factor undercounts every sloped roof.

    Exact wording

    A square of roofing covers 100 square feet of roof surface. Surface area is the plan area times the slope factor, √(rise² + 144) ÷ 12 for a rise-in-12 pitch. Divide by 100 for squares and add waste last. Example: 2,400 square feet of plan area at 6 in 12 has a slope factor of 1.118, so 2,683 square feet, 26.8 squares, and 29.5 squares with 10 percent waste, ordered as 30.

    Standard trade practice

  7. Treat a symmetrical gable roof as two equal rectangles.

    The two-rectangle shortcut works only when the ridge is centered and both sides have the same pitch. Each rectangle is the building length times the rafter length, and the rafter length is the run (half the span) times the slope factor. A 40-by-24-foot building at 4 in 12: run 12 feet, slope factor 1.054, rafter length 12.65 feet, so 2 × 40 × 12.65 = 1,012 square feet, about 10.1 squares.

    On the job

    Half the span, times the slope factor, times the length, times two, when the ridge is centered and both sides match. An off-center ridge or unequal pitches means two different runs, each figured on its own.

    Exact wording

    For a simple symmetrical gable roof with a centered ridge and the same pitch on both sides, the roof is two equal rectangles: each is the building length times the rafter length, and the rafter length is the run (half the span) times the slope factor. Example: a 40-by-24-foot building at 4 in 12 has a 12-foot run, a slope factor of 1.054, a rafter length of 12.65 feet, and 2 × 40 × 12.65 = 1,012 square feet, about 10.1 squares.

    Standard trade practice

  8. compares the field dry density to the laboratory maximum for that same soil.

    Divide the field dry density of the compacted soil by the maximum dry density a laboratory compaction test produced for that same soil, then express the answer as a percent. A 90 percent specification is met when field density reaches 90 percent of that laboratory maximum.

    On the job

    The denominator is the lab's number for that soil, not a fixed figure — the field test alone cannot say whether the backfill passes.

    Exact wording

    Relative compaction is the field dry density of the compacted soil divided by the maximum dry density a laboratory compaction test produced for that same soil, expressed as a percent; a specification such as 90 percent relative compaction is met when the field density reaches 90 percent of that laboratory maximum.

    Standard trade practice

Back to contents

Important numbers to know

Where people go wrong

Where to look it up

Anchoring and concrete
CBC Chapter 19 (1901.3 adopts ACI 318 as supplemented by 1905)
Compacted fill and geotechnical reports
CBC 1803.5.8
Lot grading
CRC R401.3
Excavation notification and safety
Title 8 §1541 (and Gov. Code 4216)
Crawl-space ventilation and ground cover
CRC R408
Attic vent clearance
CRC R806.3
U-factor definition and tables; compliance paths
Energy Code 100.1; Joint Appendix JA4; 150.1
Sound separation between units
CBC 1206.2
Asphalt shingles, flashing, valleys, drip edge; built-up roofs
CRC R905.2 and R905.9
Secondary roof drains
CBC 1502.2; CPC 1101.12.2.2

Glossary

Every term this guide defines, in one place. Each is also defined where it first appears.

Base and cap flashing
Base flashing is the lower flashing at a roof-to-wall or chimney joint; cap (counter) flashing laps down over it. Step flashing is base flashing installed as overlapping pieces along a sloped sidewall.
Benchmark
A fixed point of known elevation that a level run starts from and closes back to.
Height of instrument (HI)
The level's line of sight elevation: benchmark plus backsight.
Lift
One layer of fill placed and compacted before the next; the code limits its thickness.
Relative compaction
In-place dry density as a percent of the laboratory maximum dry density.
Scupper
An opening through a parapet that lets roof water out; a secondary scupper is the emergency overflow.
Slope factor
Sloped length per foot of run: √(rise² + 144) ÷ 12.
Square (roofing)
100 square feet of roof surface.
STC
Sound transmission class, a lab rating of a wall's airborne-sound blocking; NNIC is the field-tested counterpart.

Keep going

Test yourself: 11 questions for this guide

A paid account adds more ways to practice and prepare: study questions after every chapter, practice questions for every topic, timed practice exams, and job scenarios drawn from real jobs. A free account gets you one timed practice exam and saves your progress across devices. Here is one of this guide's questions:

A continuous footing is 18 inches wide, 12 inches deep, and 150 feet long. How many cubic yards?

Answer1.5 × 1 × 150 = 225 cubic feet; ÷ 27 = 8.3 cubic yards before waste.

Standard trade practice

Create an account

Finished reading?

When you miss a question on this topic, we'll suggest a job scenario where there is one, rather than text you've already read. Finishing every chapter counts too.